Milestones
We kicked off the Brass LNG project in 2003. When the plant is completed, it will produce quality LNG for at least 20 years.
-
2001
-
5th September, 2001
Conceptual study Memorandum of Understanding agreed by the Nigerian Government, Nigerian National Petroleum Corporation (NNPC), Nigerian Agip Oil Company (NAOC), & Phillips Oil Company Nigeria Limited (POCNL)
-
2002
-
2003
-
January 2003
Onshore plant conceptual study completed
-
30th October, 2003
NNPC, POCNL, ENI International and Chevron Nigeria Limited entered Heads of Agreement to establish the Company
-
9th December, 2003
Brass LNG Limited incorporated
-
2004
-
2005
-
2006
-
January 2006
Memoranda of Understanding for long-term LNG sales signed
-
3rd April, 2006
Environmental Impact Assessment (EIA) submitted to regulators
-
19th July, 2006
EIA Provisional Approval received from regulators
-
July 2006
Total joins as a Brass LNG Shareholder, replacing Chevron Nigeria Limited
-
20th September, 2006
Shareholders Agreement signed
-
November 2006
Final FEED completed
Plant site real estate obtained
-
2007
-
February 2007
Granting of the Brass LNG Free Zone
-
May 2007
Ground breaking ceremony by President Olusegun Obasanjo CFR
-
June 2007
Brass LNG enters a Project Management Contract with Bechtel Corporation of United States